News

7-17, Sep, 1999

ARLISS PROJECT

4, Sep, 1999

We had the last meeting for ARLISS project.

1, Sep, 1999

Rehearsal for ARLISS Project is held at TAMAGAWA-River side.

29, July, 1999

Vibration Test is held at NASDA with TIT.

6, July, 1999

CDR (Critical Design Review) is held at university of Tokyo.

18, June, 1999

Barometer Calibration has been made.

17, June, 1999

Accelerometer Calibration has been made.

17, June, 1999

Descending Test using Parachutes for ARLISS was held.

11, June, 1999

System Integration of ARLISS-CanSat#001 was made.

4, June, 1999

Nakasuka Labo. Ground Station was established.

28, May, 1999

CanSat Project was broadcast over a nation-wide network by NHK(Japan Broadcasting Corpotation).

28, May, 1999

Thermister Calibration has been made.

27, May, 1999

Gyro Calibration has been made.

25, May, 1999

CanSat activity was reported in evening edition of the Yomiuri - a Japanese newspaper publishing company.

25, May, 1999

PDR (Principal Design Review) is held at university of Tokyo.

23, Apr, 1999

ARLISS (Aeropac Rocket Launched International Student Satellites) is suggested by Prof. Twiggs.

11-15, Apr, 1999

Attend the Second International Conference on Integrated Micro/Nanotechnology for Space Applications in California, and made the presentation.(N.S)

1, Apr, 1999

Decide the name of our CanSat as Gekka-Bijin.

9, Mar, 1999

Second structual model is completed. (S.O)

22, Feb, 1999

began Extension Test. But it failed.

22, Jan, 1999

First structual model is completed. (S.O)

20, Jan, 1999

made new CANSAT web page. (K.M.)