XI-V Shipment
XI-V is exported from Japan to Russia via Netherlands for the launch. (Local time is used.)
Beginning of June/2005
--:--
CubeSats are loaded into SSETI Express.
--:--
UWE-1 integration(Photo Courtesy Mr. Neil)
22nd/May/2005
AM(JST)
Shipment team and XI-III return home safely.
ISSL side works are all complete. Start withdrawing.
18th/May/2005
PM(CET)
XI-V is installed in SSETI.
PM(CET)
Launch pad operation is explained to Mr.Neil(SSETI).
AM(CET)
TPOD (satellite ejection system) works fine.
AM(CET)
Function test is finished. Parameters are set. XI-V is polished up.
17th/May/2005
PM(CET)
Electrical inspection
AM(CET)
Visual inspection
Morning(CET)
Move to ESTEC. Integration with SSETI starts.
16th/May/2005
--:--(CET)
Standby due to ESTEC's nonworking day.
15th/May/2005
PM(CET)
Move to Leiden
PM(CET)
Coalesced with Mr.Enokuchi@Atrium at Amsterdam Airport Schiphol
10:00(JST)
Departure from Japan