XI-V Shipment

XI-V is exported from Japan to Russia via Netherlands for the launch. (Local time is used.)

Beginning of June/2005

--:--

CubeSats are loaded into SSETI Express.

--:--

UWE-1 integration(Photo Courtesy Mr. Neil)

22nd/May/2005

AM(JST)

Shipment team and XI-III return home safely.

ISSL side works are all complete. Start withdrawing.


18th/May/2005

PM(CET)

XI-V is installed in SSETI.

PM(CET)

Launch pad operation is explained to Mr.Neil(SSETI).

AM(CET)

TPOD (satellite ejection system) works fine.

AM(CET)

Function test is finished. Parameters are set. XI-V is polished up.

17th/May/2005

PM(CET)

Electrical inspection

AM(CET)

Visual inspection

Morning(CET)

Move to ESTEC. Integration with SSETI starts.

16th/May/2005

--:--(CET)

Standby due to ESTEC's nonworking day.

15th/May/2005

PM(CET)

Move to Leiden

PM(CET)

Coalesced with Mr.Enokuchi@Atrium at Amsterdam Airport Schiphol

10:00(JST)

Departure from Japan